Pembangunan Jalan SMK IT Payakumbuh

๐Ÿ‡ฎ๐Ÿ‡ฉ Indonesiaยท2016
Validated
CCPMConstruction

Case Summary

Reduced project timeline from 314 days to 235 days, achieving a 33.4% optimization in time.

Quantified Results

metric: 147 hari kalender

Source

Title
Pengendalian Waktu Proyek dengan Menggunakan Metode Critical Chain Project Management (Ccpm) (Studi Kasus: Pembangunan Jalan SMK IT Payakumbuh)
Type
academic paper
Year
2016
Confidence Score
80%