Boosting Construction
๐ฎ๐ฉ Indonesiaยท2023
Validated
CCPMConstruction
Case Summary
Improved project timeline by 20% and completed in 151 days using CCPM compared to planned 187 days.
Source
- Title
- Boosting Construction Project Timeline: The Case of Critical Chain Project Management (CCPM)
- Type
- academic paper
- Year
- 2023
- Confidence Score
- 90%