Indonesia (PT. Wijaya Karya)

๐Ÿ‡ฎ๐Ÿ‡ฉ Indonesiaยท2021
Collected
CCPMConstruction

Case Summary

Implementation of Critical Chain Project Management resulted in a 3-day reduction in project completion time and cost savings of Rp.10,907,170.03.

Source

Title
Implementation of lean construction and critical chain project management (CCPM) for waste management and work estimation on the Ciawi dam construction project
Type
academic paper
Year
2021
Confidence Score
80%