Security Accommodation Vessel Construction

๐Ÿ‡ฎ๐Ÿ‡ฉ Indonesiaยท2025
Validated
CCPMShipbuilding

Case Summary

Reduced project duration by 14.5% through the application of Critical Chain Project Management (CCPM) and buffer planning.

Source

Title
Critical Chain Project Management and Buffer Planning: Study Case at Security Accommodation Vessel Construction