Ciawi Dam Construction
๐ฎ๐ฉ Indonesiaยท2021
Validated
CCPMConstruction
Case Summary
Reduced project completion time from 18 working days to 15 working days, and cost savings of Rp.10,907,170.03
Source
- Title
- Implementation of lean construction and critical chain project management (CCPM) for waste management and work estimation on the Ciawi dam construction project
- Type
- academic paper
- Year
- 2021
- Confidence Score
- 80%