CCPMSpeed Boat Production

Case Summary

CCPM produces a faster project completion time compared to PERT method.

Quantified Results

metric: 28.5

Source

Title
OPERATIONAL RISK ASSESSMENT SHIP CONSTRUCTION CAUSES MATERIAL IMPORT USING HOUSE OF RISK (HOR) AND CRITICAL CHAIN PROJECT MANAGEMENT: CASE STUDY IN GRESIK SHIPYARD INDUSTRY