SNC-Lavalin

🇨🇦 Canada·2025
Validated
CCPMConstruction

Case Summary

The application of the CCPM method reduced the project timeline from 314 days to 235 days, achieving a 33.4% optimization in time.

Source

Title
Buffer Time Analysis in Construction Project scheduling with Critical Chain Project Management (CCPM) Method
Type
academic paper