Samarinda City Government
🇮🇩 Indonesia·2016
Validated
CCPMGovernment
Case Summary
The use of CCPM resulted in a cost savings of Rp 150.985.476,71 by not using the buffer.
Quantified Results
metric: 44.5 days of project buffer
Source
- Title
- Determination of critical chain project buffer based on information flow interactions
- Type
- academic paper
- Year
- 2016
- Confidence Score
- 90%