PT Wijaya Karya
🇮🇩 Indonesia·2016
Validated
CCPMConstruction
Case Summary
Implementation of CCPM resulted in a 37% reduction in project duration and cost savings of Rp.10,907,170.03.
Quantified Results
metric: 147
Source
- Title
- Pengendalian Waktu Proyek dengan Menggunakan Metode Critical Chain Project Management (Ccpm) (Studi Kasus: Pembangunan Jalan SMK IT Payakumbuh)
- Type
- academic paper
- Year
- 2016
- Confidence Score
- 80%