Boosting Construction

🌐 ·2023
Validated
CCPMConstruction

Case Summary

Achieved an economy of 36 days (around 20%) and completed the project in 151 days using CCPM compared to the planned 187 days.

Source

Title
Boosting Construction Project Timeline: The Case of Critical Chain Project Management (CCPM)
Type
academic paper
Year
2023