Gresik Shipyard
๐ฎ๐ฉ Indonesiaยท2021
Validated
CCPMShipbuilding
Case Summary
Used Critical Chain Project Management (CCPM) to reduce project delay and save time duration from activities schedule by 50%.
Quantified Results
metric: 50% time duration saved
Source
- Title
- OPERATIONAL RISK ASSESSMENT SHIP CONSTRUCTION CAUSES MATERIAL IMPORT USING HOUSE OF RISK (HOR) AND CRITICAL CHAIN PROJECT MANAGEMENT: CASE STUDY IN GRESIK SHIPYARD INDUSTRY
- Type
- academic paper
- Year
- 2021
- Confidence Score
- 80%